Project Roadmap

13-week execution plan for EO-1 replication on bimanual LEGO assembly

Start:Jan 16, 2026
End:Apr 4, 2026
Duration:13 weeks

Phase Overview

Click any phase to navigate to its detailed timeline

Phase 0: Foundation & Setup

Environment setup, literature deep-dive, detailed technical planning

GPU:~4-15 hrs
Focus:Development, testing
Duration:Week 1
Start
Jan 16
0.1

Development Environment Setup

2 days
Set up GPU cluster access and job schedulerWorking SLURM/PBS scripts
Install CUDA, cuDNN, PyTorch 2.xVerified GPU training capability
Configure DeepSpeed ZeRO-1Multi-GPU training test
Set up experiment tracking (W&B/MLflow)Experiment logging working
Configure version control and project structureGit repo with CI/CD
0.2

MuJoCo Sim Stack + Visualization Workflow

3 days
MuJoCo Runtime InstallationStable MuJoCo environment on lab PC
Interactive Viewer WorkflowDebug-mode viewer for visual inspection
Headless Offscreen RenderingBatch rendering pipeline (RGB, depth)
Sim Smoke Tests SuitePush-button test suite with CI integration
Asset Pathing & Loader ContractStrict asset directory layout and linter
Cluster Compatibility SmokeVerified headless sim on cluster
0.3

Literature Deep Dive

5 days
Study EO-1 paper in detail (architecture, training, data)Annotated notes, implementation questions
Study pi0/pi0.5 as referenceComparative analysis notes
Understand flow matching theoryMathematical understanding document
Review Qwen 2.5 VL architectureVLM backbone familiarity
Study interleaved training methodologyTraining recipe understanding
End
Jan 25
Phase 0 Milestone

Environment Ready

Simulation running, LEGO physics working

Go/No-Go: Scripted policy >50% success

Phase 1: Simulation Environment

Complete LEGO assembly simulation environment with bimanual robot

GPU:65–155 hrs
Focus:Development, testing
Duration:Week 2-4
Start
Jan 26
1.1

Robot Model Integration

6 days
Import/create bimanual robot URDF/MJCFWorking robot model in sim
Configure joint limits, dynamics parametersPhysically accurate robot
Set up end-effector models (SAKE EZGripper)Functional end-effectors
Verify kinematics match target (Alex-compatible)Kinematics validation report
1.2

LEGO Environment Creation

12 days
Create LEGO block models (2x2, 2x4, 2x6 bricks)Accurate LEGO meshes with studs
Configure stud/tube contact physicsBlocks that connect realistically
Create baseplate and workspaceComplete assembly environment
Add multiple camera viewpointsMulti-view rendering
Implement block spawning and resetEpisode management
End
Feb 18

Phase 2: Data Pipeline

Generate training data including interleaved vision-text-action sequences

GPU:TBD hrs
Focus:Development, testing
Duration:Week 3-5
Start
Jan 24
2.1

Robot Trajectory Data Generation

5 days
Generate 10K scripted demonstration episodesBase trajectory dataset
Implement parallel data collectionEfficient data generation
Add failure cases and recovery demonstrationsFailure trajectory dataset
Quality control and filteringCleaned dataset
2.2

VLM-Based Annotation Pipeline

4 days
Design annotation schema (following EO-Data1.5M)Annotation specification
Set up VLM for trajectory annotation (GPT-4V/Qwen-VL)Annotation system
Generate task descriptions and reasoning QALanguage annotations
Validate annotation qualityQuality metrics
2.3

Interleaved Data Construction

5 days
Implement interleaved sequence construction (following EO-1)Interleaved data generator
Create temporal reasoning data (task planning, verification)Temporal reasoning subset
Create spatial reasoning data (trajectory prediction, grounding)Spatial reasoning subset
Create free chatting format dataMixed format subset
End
Feb 14
Phase 2 Milestone

Data Ready

10K trajectories + interleaved data

Go/No-Go: Data loads correctly, formats verified

Phase 3: Model Architecture

Implement EO-1 architecture with modifications for LEGO task

GPU:TBD hrs
Focus:Development, testing
Duration:Week 4-6
Start
Jan 31
3.1

VLM Backbone Integration

4 days
Load Qwen 2.5 VL pretrained weightsWorking VLM backbone
Configure tokenizer and visual encoderTokenization pipeline
Verify VLM inference worksVLM sanity check
Profile memory usage on A100Memory characterization
3.2

Action Head Implementation

5 days
Implement flow matching action headFlow matching module
Implement robot state projectorState embedding module
Implement noisy action projectorAction embedding module
Configure action chunk size (16)Chunked action generation
End
Feb 21
Phase 3 Milestone

Model Ready

Full architecture implemented, forward pass works

Go/No-Go: Inference produces reasonable actions

Phase 4: Training Infrastructure

Complete, correct training pipeline (even if not run to completion)

GPU:TBD hrs
Focus:Training infrastructure verification
Duration:Week 5-7
Start
Feb 7
4.1

Loss Function Implementation

3 days
Implement autoregressive loss for textCross-entropy loss module
Implement flow matching loss for actionsFlow matching loss module
Implement combined loss with balancingCombined training objective
Verify loss computation on sample batchesLoss sanity checks
4.2

Distributed Training Setup

3 days
Configure 8-GPU training scriptsMulti-GPU training working
Implement proper distributed samplingCorrect data sharding
Test distributed checkpointingDistributed save/load
Profile training throughputThroughput benchmarks
End
Feb 28
Phase 4 Milestone

Training Ready

Complete pipeline verified on small scale

Go/No-Go: Loss decreases on mini-training

Phase 5: Training Execution

Execute training at scale, monitor and adjust

GPU:TBD hrs
Focus:Main training (~2-3 weeks on 8xA100)
Duration:Week 7-10
Start
Feb 21
5.1

Initial Training Run

7 days
Launch full training on 8xA100Training in progress
Monitor loss curves and metricsContinuous monitoring
Identify and fix early issuesIssue resolution log
Adjust hyperparameters if neededTuned hyperparameters
5.2

Continued Training with Adjustments

10 days
Continue training with any necessary adjustmentsImproved training run
Implement curriculum learning if beneficialCurriculum schedule
Save multiple checkpoints for evaluationCheckpoint library
Document training decisionsTraining decision log
End
Mar 21
Phase 5 Milestone

Training Checkpoint

Midpoint training evaluation

Go/No-Go: >50% LEGO success, loss stabilized

Phase 6: Evaluation & Benchmarking

Comprehensive evaluation on LEGO tasks and standard benchmarks

GPU:TBD hrs
Focus:Evaluation, ablations, fine-tuning
Duration:Week 9-11
Start
Mar 7
6.1

LEGO Task Evaluation

5 days
Evaluate on all LEGO task configurationsTask success rates
Measure precision and efficiency metricsDetailed metrics
Analyze bimanual coordination qualityCoordination analysis
Document failure modesFailure taxonomy
6.2

LIBERO Benchmark Evaluation

3 days
Set up LIBERO benchmark environmentLIBERO running
Evaluate model on all 4 suitesLIBERO scores
Compare against reported EO-1 numbersComparison analysis
6.3

Ablation Studies

5 days
Ablate interleaved vs standard trainingAblation results
Ablate flow matching vs autoregressive actionsAction head comparison
Ablate action chunk sizesChunk size analysis
Document findingsAblation report
End
Mar 28
Phase 6 Milestone

Evaluation Complete

Full benchmark results

Go/No-Go: Performance characterized, documented

Phase 7: Fine-tuning Experiments

Understand fine-tuning dynamics and task adaptation

GPU:TBD hrs
Focus:Evaluation, ablations, fine-tuning
Duration:Week 10-12
Start
Mar 14
7.1

Task-Specific Fine-tuning

5 days
Fine-tune on specific LEGO kitSpecialized model
Compare pretrained vs fine-tunedFine-tuning effectiveness
Analyze catastrophic forgettingForgetting analysis
Document optimal fine-tuning recipeFine-tuning guidelines
7.2

Few-Shot Adaptation Experiments

4 days
Test with 10, 50, 100 demonstrationsFew-shot learning curves
Compare to training from scratchData efficiency analysis
Identify minimum data requirementsData requirement guidelines
End
Apr 4

Phase 8: Sim-to-Real Preparation

Prepare for future real-robot deployment on IHMC Alex

GPU:TBD hrs
Focus:Documentation, packaging
Duration:Week 11-13
Start
Mar 21
8.1

Sim-to-Real Gap Analysis

3 days
Document all simulation simplificationsGap analysis document
Identify critical transfer risksRisk prioritization
Plan domain randomization extensionsDR improvement plan
Estimate real-world performanceTransfer prediction
8.2

Alex Action Space Mapping

3 days
Document Alex kinematic structureAlex specification document
Design action space mapping (sim -> Alex)Mapping specification
Identify embodiment differencesEmbodiment gap analysis
Plan adaptation strategyAlex adaptation plan
8.3

Project Documentation and Handoff

3 days
Complete code documentationDocumented codebase
Write project reportTechnical report
Create reproduction instructionsREADME and guides
Package trained models and dataShareable artifacts
End
Apr 4
Phase 8 Milestone

Project Complete

Documentation, models, code packaged

Go/No-Go: Reproducible, ready for next phase

Success Criteria

Evaluation benchmarks for project outcomes at Week 13

Minimum Viable Outcome

  • Complete, documented training pipeline (runnable if not fully trained)
  • Model achieving >50% on simple LEGO tasks in simulation
  • LIBERO benchmark evaluation completed
  • Comprehensive documentation of approach and findings

Target Outcome

  • Model achieving >70% on LEGO tasks across difficulty levels
  • Competitive LIBERO scores (within 10% of reported EO-1)
  • Generalization testing completed
  • Fine-tuning experiments completed
  • Sim-to-real readiness documented

Stretch Goals

  • >85% LEGO task success
  • Match or exceed EO-1 LIBERO numbers
  • Preliminary dual-system extension implemented
  • Real-robot demonstration (if Alex/Franka available early)

Success Metrics

Evaluation criteria for task completion, efficiency, and generalization

Primary Metrics

Core success measures for task completion

MetricDefinitionTarget
Task Success Rate% of assemblies completed correctly>85%
Block Placement Accuracy% of blocks placed in correct position/orientation>95%
Connection Quality% of blocks properly seated (not loose)>98%

Efficiency Metrics

Performance and recovery measures

MetricDefinitionTarget
Completion TimeTime from start to verified completionTBD
Attempt EfficiencySuccessful placements / total attempts>90%
Recovery Rate% of errors successfully corrected>70%

Generalization Metrics

Measures of robustness and transferability

MetricDefinition
Kit GeneralizationPerformance on unseen assembly configurations
Block GeneralizationPerformance with novel block colors/sizes
Instruction GeneralizationPerformance with rephrased/novel instructions
Visual GeneralizationPerformance under lighting/background changes